What are the installation requirements of conveyor belt manufacturers

2020-10-17 12:00:00
times

1. According to the design requirements, the tail of the belt conveyor is installed. After the tail is installed, the head of the transfer machine is set on the tail of the belt conveyor, and the tail of the belt conveyor is fixed. Nylon conveyor belt

2. Starting from the tail of the machine, an H-frame is placed every 3M, and the belt is placed at about 40m. It is bypassed from the tail roller, and then suspended in turn. The longitudinal beam, triple roller (g ǔ n) and straight roller are aligned. With the installation of the belt, it is removed and transported out, leaving a log for supporting the back and top materials. The role of idler is to support the weight of conveyor belt and material. The operation of idler must be flexible and reliable. Reducing the friction between conveyor belt and idler plays a key role in the service life of conveyor belt which accounts for more than 25% of the total cost of conveyor. Although the idler is a small part in the belt conveyor and its structure is not complex, it is not easy to make high quality idler.

3. After the installation of the belt conveyor body, the installation of the head is started.

4. The machine head installation shall check the foundation size carefully according to the installation construction drawings and relevant technical documents, and find out the installation center line and elevation of the equipment.

5. Clean the installation site, foundation surface and foundation bolt (composed of head and screw) holes to ensure the quality of secondary grouting after installation.

6. Place the base of the equipment or components to be installed on the position to be installed according to the requirements of the manual, and after leveling and alignment, install the foundation bolts (composed of head and screw) for secondary grouting. Nylon conveyor belt




7. For head installation, first align the base of the main and auxiliary driving rollers with the installation hole. After connecting the extended base with the base, align the datum hole, install the main and auxiliary driving rollers, fix the H-frame, lift the main and auxiliary driving rollers, fix them to the H-frame with M42 bolts, and then install other accessories of the head frame. According to the properties of the covering rubber, the annular conveyor belt can be divided into cold resistant type, acid resistant type, alkali resistant type, oil resistant type, wear-resistant type, etc. This product is made of nylon canvas by calendering, molding, vulcanization and other processes.

8. After the head frame is installed, the unloading arm is installed, the position of the unloading roller is adjusted, the foundation bolt is installed after leveling and alignment, and the secondary grouting is carried out.

9. Lift the reducer and motor, support the taper hole of the reducer on the shaft head of the main drive drum with the same taper, add key connection, tighten the end with bolts (composed of head and screw), and fix the middle and rear parts on the extension base with screws relying on the support under the coupling cover. According to the properties of the covering rubber, the annular conveyor belt can be divided into cold resistant type, acid resistant type, alkali resistant type, oil resistant type, wear-resistant type, etc. This product is made of nylon canvas by calendering, molding, vulcanization and other processes.

10. Install the belt storage bogie, which is connected with the head frame by bolts, and the connecting frame is connected with the head frame and belt storage bogie by bolts.

11. Gradually (step by step) install the belt storage rack, change the direction of the drum, idler (g ǔ n) car, traveling car tension device.

12. Installation of electrical equipment, belt protection, belt head fire test run, after normal operation, began to install the conveyor belt.

13. The belt conveyor is put into trial operation and the deviation is adjusted comprehensively.